UpDATE: October 8, 2018

Henrico County had a hearing on September 26, 2018 for our submitted Design Development drawings.  No one from the community came forward to contest the church's expansion plans.  The County approved moving forward with the provision that we install a sidewalk on the length of Horsepen Road. A variance to this ordinance was requested but denied by the county. Our budget estimate for that addition is $18,000. The architect has been given approval to file Construction Documents with the county.  The Building Team has sent out a Request For Proposals to three Construction Companies for cost estimate and pre-construction and construction phases. We anticipate the whole project will be put to a congregational vote in January 2019.


update from September 4, 2018


The Building Team met with the architect on August 29th, 2018 to go over the Design Development Drawings.  We went over our current design plans and had a very productive meeting.  At this time, we are waiting on an updated construction cost estimate from Taylor & Parrish, a construction company that the building team is working with.  We should receive the estimate by mid September.  With the new estimate we will have our direction for moving forward.  By early October Construction Documents will be filed with the county.  Any feedback or questions should be emailed to epiphanyvision2020@gmail.com or ask any member of the team. We are set to bring this to a vote for the congregation in late 2018 or very early 2019.




update from June 25, 2018


The architect has finished his first round of schematic designs and is revising them for design development with the help of Taylor and Parrish, a construction firm. This is intended to keep potential future construction costs as low as possible. Finalized construction drawings will be produced by the end of the summer. The initial scope of the project has changed to concentrate first on the improvements to the front of the building (the gathering areas, new restroom facilities, and new office suite) and a much-needed unisex bathroom on the second floor of the education wing. Other aspects of the original design can be added later when additional funding as been secured.


Congregation Council has set the construction cost limit at $2.6 million, but the total project cost will be higher and will include "soft costs" such as hiring a construction manager, permit costs, furnishings, and wiring for new internet/technology systems.


Construction is scheduled to begin in early 2019, pending final approval by vote of the congregation at a meeting in fall 2018.